| 6.1 Noise Control |
|
|
|
| Written by Traders Association | |
| Tuesday, 08 July 2008 06:52 | |
6 Noise6.1 Noise Control(a) The Contractor shall have a general duty to take all practicable measures to minimise nuisance from noise. The noise limits specified in this section or which may be otherwise agreed with The City of Edinburgh Council shall not be regarded as a licence to make noise up to the stated limit.(b) Subject to the specific requirements of The City of Edinburgh Council, the following minimum requirements shall be met: (i) During normal working hours, as defined in Clause 3 (a), the maximum noise levels measured 1 metre from any occupied dwelling or other building used for residential purposes, generated by construction plant and equipment shall not exceed the following limit: Monday to Saturday (inc.) 1900-2200 LAeq 3 hours 65 dB
(c) In order to ensure that the best practicable means are used to meet the levels set out above, a programme of on-site monitoring by a suitably qualified practitioner shall be agreed between the Contractor, tie and The City of Edinburgh Council. This monitoring programme shall include the location and frequency of readings and will define to whom the results shall be made available. Monitoring will be undertaken at locations identified in the Environmental Statements as those where mitigation measures may be necessary to avoid significant noise disturbance. (d) In exceptional difficult circumstances essential work causing noise above these limits may be permitted with the prior approval of tie and The City of Edinburgh Council. Application for prior approval must be made at least two weeks in advance of the relevant works commencing, and must be fully justified and kept to the minimum necessary. Conditions may be attached to any permission for such works. (e) In the event that measurements indicate noise has exceeded the limits in paragraph (b) of this clause the Contractor shall stop the operation in a safe manner and take all practicable measures to prevent recurrence. If this does not enable the limits to be met exceptional permission must be applied for under the terms of paragraph (b) of this clause. (f) Without prejudice to the other requirements of this Section, the Contractor shall comply with the recommendations set out in BS 5228 'Noise Control on Construction and Open Sites' insofar as these are reasonably practicable and applicable to the construction works and in particular with the following requirements: (i) All vehicles and mechanical plant used for the purpose of the work shall be fitted with effective exhaust silencers and shall be maintained in good and efficient working order.(g) Without prejudice to this Section, the Contractor shall comply with the City of Edinburgh Department of Environmental and Consumer Service's document Construction Site Noise: A Guide for Contractors, August 2000 (or current issue, if subsequent amendments issued), and shall liaise with that department in accordance with the requirements therein. |
|
| Last updated ( Tuesday, 19 August 2008 21:08 ) |